Vinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo SliderVinaora Nivo Slider

Application for testing Self-powered relays SEG (Woodward) WIP1 and WIC1

Application Note

Self-Powered-Relay (SPR) takes its supply from the  CT-s connected and also the energy for tripping the breaker. SPR  either has special CT made for the relay or is made to be used directly with standard CT-s.

There are differences in how to set Sverker 900 when testing SPR that must be noticed.
1. The level of pre-fault current and time needed for pre-fault.
2. The pickup level for trip signal if not dry contact is used.

Here secondary testing of SEG relay (formerly Woodward) WIP1 and WIC1 will be described.

Application for Testing Self Powered Relays SEG (Woodward) WIP1 and WIC1

 

2025 Electrical Testing Expert Catalog

Megger Transformer Catalogue

Megger Cable Catalogue

Industrial Maintenance Catalog 2024

Megger Power Catalog

Merytronic

Portable Devices

Fluke 2025 - 2026 Product Guide

Solucao Product Catalog

Orion Electrical Safety Rubber Equipments Catalogs

BETE Electrical Construction Tools 2025

MULTI Main Sales Product Line 2026

ANHU Electric Catalog